 |
 |
 |
 |
| | De-rating
Maximum Allowable Working Pressure (MAWP) on unfired
pressure vessels
To eliminate
confusion for inservice inspectors, the practice of
de-rating the maximum allowable working pressure (MAWP)
for unfired pressure vessels will no longer be allowed
or used. This practice was never part of our state boiler
law, and guidelines and procedures for de-rating were
never uniform or consistent. A "de-rated" unfired pressure
vessel could be reinstalled at another location and
operated at the original MAWP, causing a serious safety
hazard. The inservice inspection guidelines in the NBIC
adopted by the state does not address de-rating.
L&I cannot,
and will not, accept responsibility for authorizing
owners/users to operate unfired pressure vessels in
a corroded, deteriorated, unsafe condition. Any thinning
in the unfired pressure vessel shell or heads below
the Code-calculated minimum thickness would be considered
unsafe. Any unfired pressure vessel found in this condition
shall be "Red Tagged" VIOLATION-DO NOT USE, by the inservice
inspector. The unfired pressure vessel must be immediately
removed from service until the following conditions
are met:
- A qualified person determines the ASME Code-calculated
minimum thickness required (tm) based on UT thickness
readings by a qualified NDE Company to the original
code of construction.
- The calculations and UT thickness readings are
submitted to the Chief Boiler Inspector for review
and approval. A record of the results will be entered
into the "Jurisdiction Online" database.
- The unfired pressure vessel is subjected to an
internal inspection or other required inspections
necessary to satisfy the inservice inspector.
- Repairs are done by a qualified "R" stamp certificate
holder if weld repairs are necessary to restore the
unfired pressure vessel to it's original condition.
- The completed "R-Form" and Traveler is sent to
the Chief Inspector for review and filing.
If repairs
are not possible, the unfired pressure vessel must be
replaced. |
 |
 |
 |
 |
 |
 |
 |
 |
Next Board of Boiler Rules meeting
November
15-16 , 2004
Room 3, L&I
Service Location, Tacoma
|
 |
 |
 |
 |
 |
 |
 |
 |
 |
For
questions about boiler regulations, fees and forms,
please call:
Tony
Oda, Technical Specialist
Phone: 360-902-4983
E-mail: odaa235@LNI.wa.gov
Eldolyne
Gibson, Secretary Administration
Phone: 360-902-5271
E-mail: gibe235@LNI.wa.gov
Karol
Conly, Customer Service Specialist (Supervisor)
Phone: 360-902-5273
E-mail: conk235@LNI.wa.gov
Kay Piesch, Customer Service Specialist
Phone: 360-902-5272
E-mail: piek235@LNI.wa.gov
Annabel Schmidt, Customer Service Specialist
Phone: 360-902-5267
E-mail: schc235@LNI.wa.gov
|
 |
| |
|
|
|
 |
 |
 |
 |
| |

Q:
How does the State of Washington determine the cubic
foot volume (?) of a jacketed kettle under its jurisdiction?
A: L&I, with concurrence of the Washington State
Board of Boiler Rules, measures a jacketed kettle by
multiplying the outside diameter by the overall length
to get the cubic foot volume. That is, the volume
of the jacket
including the volume of the contents of the kettle is
used as the appropriate measurement.

Q: What are the requirements for pool heaters
within the state's jurisdiction?
A: The state of Washington does not use the term pool
heater. We consider these units to be water
heaters or boilers.
For units sized from 0 – 200,000 Btu, L&I
requires them to be built to a
nationally recognized standard like AGA, ANSI, or UL.
Units sized
more than 200,000 Btu must be ASME Code-stamped and
National Board registered.
Units under
400,000 Btu are not required to meet the requirements
of ASME CSD-1 part CF.
|
|
| |
|
|
Fall 2004
Edition 1
| |
| |
 |
| |
Labor and Industries, Dept. of
Boiler Program
Office: 360-902-5270
Fax: 360-902-4292
The Boiler Room is a quarterly e-newsletter from the
Department of Labor and Industries' Boiler program.
Click here to
be added to our distribution list. |
|
|
|